Demolition & Abatement Schedule

  • Project Schedule (Demolition and Abatement)*

    1. Maplewood Building Abatement Prep: March 4-8 (dates flexible)
    2. UST Removal (One Week): April 1-5
    3. Abatement (Three Weeks): April 1-19
    4. Building Demolition (Six Weeks)
      1. Concessions Building / Storage Building: (One Week) April 22-26 (latest dates)
      2. Transportation Building (One Week): April 22-26 (latest dates)
      3. Maplewood School (Five Weeks): April 22-May 24
    5. New Construction of Transportation Facility: April 29 (Pending Village of Cary ZBA and Stormwater Permit).

    *This is the Tentative Schedule that will be updated as needed

    Update – March 22 2024
    The District received communication from the Village of Cary that the Zoning recommendation for the Maplewood Property made by the Zoning, Planning, and Appeals Board will be reviewed on April 16th.   If the Village of Cary approves our request, the matter would be referred back to the ZPA for consideration of our variance requests.  Full resolution to this matter may not happen until late May, thus substantially impacting our construction timeline.    The District continues to work vigilantly and in collaboration with the Village to see if this can be resolved in an expedited fashion.  Further updates will be published as they become available.

    Update – March 21 2024
    In order to move forward with the demolition of Maplewood School and the construction of our new transportation facility, the District needed to seek zoning changes to be compliant with village code. Work on our application began in December and was  based on input received from village staff, who reviewed our plans for the site. Our application was considered at the Zoning, Planning, and Appeals Board at their March 14th meeting. Unfortunately, the ZPA recommended the Village Board not approve our request for zoning relief. The Village Board is scheduled to take action on our application at their April 2nd meeting. This unfortunately places an indefinite pause on both the demolition of Maplewood School and construction of the transportation facility.  The District remains hopeful that it will receive approval for its zoning application on April 2nd, allowing the process to continue to move forward. The timeline below will be updated as new information is made available.